FARMINGTON — Voters approved new ventilation and air conditioning for the town's four elementary schools as one package in April. The work will not come all at once.
The district expects to start with one or two schools next summer, its facilities director told the Board of Education on Monday, and board members pressed staff on why all four can't be done together.
The board took four votes, one each for West District, East Farms, Union and Noah Wallace, the district's four K-4 schools without full air conditioning. Each approved that school's educational specifications, the document that tells the state what a building project is and why students need it. The district plans to apply for state grants for all four in a window that runs Tuesday, Dec. 1, through Thursday, Dec. 10.
Voters approved $14,339,152 for the four projects at the April 30 referendum. The state reimburses Farmington 31.79 percent of an eligible school project's cost this fiscal year, said Sam Kilpatrick, the director of facilities. Once the state commits to a grant, the district has two years to start the work.
Why not all four at once
Each school needs upgrades to its site utilities as well as new ventilation equipment, Kilpatrick said. The plan is one or two schools next summer and, within the two years, at least the utility work at all four, which counts as starting construction.
"What would prevent us from doing all four schools at once?" one board member asked, adding that a parent at a school left for later would want to know.
Staff gave several reasons. Design has run a little over a year and is still being worked out, including plans for hazardous materials. The district has limited capacity to manage four buildings at a time and only eight weeks of summer to work in. Summer programs, including parks and recreation, use the buildings. And because the state treats the work as four separate projects, the district could end up with four contractors, or one contractor stretched across four jobs.
Dan Zittoun, the assistant superintendent of finance and operations, said the referendum budget assumed one building a year for four years, with rising costs built in. Finishing sooner would leave the district "ahead of the game," he said, but he wanted each project done right and with proper oversight. A board member asked staff to come back with what it would take to finish all four as quickly as possible.
Members also asked whether the state money was certain. Staff said the district had applied twice under an earlier state ventilation grant program and fallen short both times; that program required having the money in hand and finishing the work within a year and a half. Ventilation work now goes through the same reimbursement process as a roof replacement, staff said. If a surprise turns up mid-project, money from the project's contingency spent on the problem, rather than on expanding the approved work, can still be reimbursed at the same rate.
It was Kilpatrick's last meeting. Zittoun said he wanted whoever the district hires next to stay, and not to run "before I tell them, hey, by the way, get four elementary HVAC projects done this one summer."
"It's not why I'm leaving, Dan," Kilpatrick said.
A first look at next year's budget
Earlier in the meeting, the board approved the guidelines, priorities and calendar for building the 2027-28 school budget.
The district's two-year forecast puts next year's budget at $91,314,224, up $4,455,670, or 5.13 percent, from this year's $86,858,554, and the following year's at $96,158,338, up 5.30 percent. Zittoun called the forecast "a very kind of raw kind of ballpark." Its biggest assumption, he said, is a 15 percent increase in health insurance, and the district is getting early guidance from One Digital that the increase will be significant.
About 89 percent of the budget is set by contracts, he said, and administrators were told to plan for 3.7 percent inflation on supplies. The board's budget workshops run Saturday, Jan. 30, through Wednesday, Feb. 3, and its budget goes to the town manager Friday, Feb. 5.
This coverage is supported by Farmington Storage, 155 Scott Swamp Road, the only storage facility in Connecticut with Museum air. 860.777.4001 📦
Jack Beckett has reported on enough school building projects to know that "educational specifications" means paperwork, and that the paperwork is what gets the state to pay. He finished this one on his second coffee. ☕
The Farmington Mercury covers Farmington from the records up: the school board vote on the ventilation plans, the budget forecast on page 29, the arrest log the town posts and then overwrites. Our motto is "Always last to breaking news," and we are comfortable there. Find us at farmingtonmercury.com and tell a neighbor. 📰