Farmington Finished Rebuilding the Yukon Pump Station.
Jack Beckett·
The pump station that turned up corroded pipe in June is now, per the superintendent, 100 percent done, short of calibrating the new flow meter. The treatment plant, meanwhile, posted one of its lowest nitrogen months on record. The next big number arrives in September, when the town expects a hard cost estimate for the MDC pump station.